Project Timeline

Project Phasing MapS

Click on the links below to view maps of what construction activities began in 2010 and what construction activities will begin in the next three years of the project. Construction schedules are subject to change.

What can you expect to see IN the next three months?

SH 114 and SH 121 West of Main Street

  • FM 1709: Work on FM 1709 Bridge has begun. After January 1, 2012, we will change the traffic pattern at FM 1709 to allow for major construction on the new bridge that will connect Northwest Highway to FM 1709.
  • SH 26: Our drainage, utility, grading (dirt), intersections and bridge crews are all currently working in the SH 26 area.
  • Northbound SH 26 to eastbound SH 114 director connector bridge: Crews will begin foundation and column work on this new bridge.
  • Eastbound SH 114 to southbound SH 121 flyover bridge: We are currently placing bridge girders (horizontal bridge beams) on the eastbound SH 114 to southbound SH 121 flyover bridge. This bridge will be complete by the end of 2013.
  • William D. Tate Avenue: Bridge crews will work on the second half of the William D. Tate Bridge, which will be complete in the last quarter of 2012.

 

SH 114/121 between Main Street and International Parkway

  • Main Street: Main Street Bridge will be substantially complete in December 2011. Full completion at the Main Street intersection is tentatively scheduled for the last quarter of 2012.
  • Texan Trail: Lighting crews will install temporary signals at Texan Trail in preparation for the bridge work that will begin in early 2012.

 

SH 121 North of DFW Airport

  • Drainage, grading (dirt), paving and bridge crews will work on the new northbound International Parkway to eastbound SH 114 ramp.
  • Bridge crews will continue work on the new westbound SH 114 bridge to southbound International Parkway into DFW Airport.
  • We will also perform column and cap work on the new southbound International Parkway bridge to eastbound SH 114.
 
PROJECT MILESTONES

Click here to see a checklist of major pieces of construction that we've started and finished.

Recently Completed Milestones

  • The first half of William D. Tate Bridge is complete. Traffic is now on this new construction while bridge crews work to complete the second half of the bridge.
  • Crews opened two new pieces of construction near DFW Airport in November 2011: the southbound International Parkway bridge over SH 114 and eastbound SH 114 ramp to southbound International Parkway into DFW Airport.
  • Traffic is now traveling on new westbound SH 114 frontage road construction from William D. Tate Avenue to FM 1709; this new frontage road goes over SH 26 and the DART rail line.
This site is best viewed with IE 6 or greater | Click to download latest version of IE